Portfolio Risk Management How to develop it

0 votes

Hello everyone! I'm defining a Portfolio Risk Management but I'm new at the topic and I have some doubts. Anyone has done it before and can help me?


My question: Example of metrics for overall portfolio risks (without making risk management on each project?
 

Aug 12, 2020 in PMP by anonymous
• 65,910 points
86 views

1 answer to this question.

0 votes


You can derive many metrics for your portfolio depending on your need. For example:

(1) Number of risky projects - a simple measure
(2) Number of cross-project risks - those risks that are capable of causing risks in other projects
(3) Depth of related risks tree - if you have (2), then you can estimate how deep a risk trigger could go

etc.

I understand that some project risks could also be portfolio-level risks. But, the PM has to ensure the success of each project. Therefore, I don't think that there is a way out of risk assessment for each project within the portfolio.

answered Aug 13, 2020 by Raina Neman

Related Questions In PMP

0 votes
1 answer

Portfolio Risk Management: How to develop it?

A portfolio is not about projects at ...READ MORE

answered Aug 5, 2020 in PMP by David Samon
101 views
0 votes
1 answer

What are all Various Risk Status in Project?

To be honest, Ganesh, I probably would not think ...READ MORE

answered Aug 13, 2020 in PMP by Richa sharma
2,190 views
0 votes
1 answer
0 votes
1 answer

How to simplify project management?

It really depends on whether there is ...READ MORE

answered Aug 13, 2020 in PMP by Roshni
• 10,480 points
74 views
0 votes
1 answer

Project Management Sessions to create awareness

Create an attractive presentation (based on the ...READ MORE

answered Aug 13, 2020 in PMP by Reshma
94 views