If we have two managers in a project one functional manager and one project manager who will have more authority on the project

0 votes
If we have two managers in a project, one functional Manager and one Project Manager, who will have more authority on the Resource selection, daily deliverables etc.,
Aug 11, 2020 in PMP by anonymous
• 19,610 points
1,299 views

1 answer to this question.

0 votes
It depends on the organizational structure of the enterprise.

If the organizational structure is functional, the functional manager will have more authority.

In a weak matrix, also functional manager has high authority, in the balanced matrix, both project manager and functional manager share responsibilities (for example both manage budget), in the strong matrix, a project manager has an authority moderate to high and controls the budget, and finally in projectized organizational structures project manager has high to almost total authority.
answered Aug 11, 2020 by Louis

Related Questions In PMP

+1 vote
1 answer

How do I become a Project manager with no experience?

Since you don't have any prior experience ...READ MORE

answered Jul 22, 2020 in PMP by Sirajul
• 59,230 points
802 views
+1 vote
1 answer

Is Project Management a good career?

Definitely, project management is a great career ...READ MORE

answered Jul 23, 2020 in PMP by Sirajul
• 59,230 points
922 views
+1 vote
1 answer
+1 vote
1 answer

Perfect Project Manager

In my view, perfection is impossible for ...READ MORE

answered Jul 29, 2020 in PMP by Louis
559 views
0 votes
2 answers

What are the key key ingredients to delivering a successful project ?

1. Executive Sponsorship 2. People 3. Culture 4. Clearly defined ...READ MORE

answered Aug 11, 2020 in PMP by Zara
903 views
webinar REGISTER FOR FREE WEBINAR X
REGISTER NOW
webinar_success Thank you for registering Join Edureka Meetup community for 100+ Free Webinars each month JOIN MEETUP GROUP